DYOR Power Feasibility Study
The next best thing to a utility load study.
We estimate how much power a site can realistically get, how soon, and what upgrades it may need, using public utility filings, transmission and substation data, and comparable sites. It costs about a third of a traditional study.
How much power
A realistic estimate of the capacity your site can get, not a best-case guess.
How soon
Estimated time to energization for each capacity tier.
What upgrades
Distribution and transmission upgrades the site may need to get there.
As much as possible for your money
This is not a formal load study, so we give you as much information as we can for what you pay. You get every number, map, contact, and citation we find, so you can make a confident go/no-go decision before spending on a utility study.
Every provider, side by side
If more than one power provider serves or could serve the site, the report covers every one of them and compares them side by side.
What's included
Deliverables in every study
- Site facts and location map
- Every power provider serving or near the site, with territory boundaries
- Side-by-side provider comparison: available capacity, timeline, upgrade needs, and rates where public
- Nearest substations and transmission lines with voltage and distance
- Power estimates in tiers: available today, with distribution upgrades, with new transmission
- Estimated timeline to energization for each tier
- Known obstacles: moratoriums, zoning, queue backlogs, water limits
- Feasibility verdict
- Contact list with names, titles, and phone numbers for each utility, the county, and economic development
- Recommended next steps, including how to request a formal load study from each utility
- Sourced citations for every finding
Every completed study is delivered as three files: the full report, a one-page executive summary, and the multi-provider comparison table. View a redacted sample
Disclaimer: This is an independent pre-screen estimate, not a utility load study or interconnection approval. Final capacity is determined only by the utility.
What you get
See a completed study
Every order includes all three documents: the full report, the one-page executive summary, and the provider comparison.